Ryde Pierhead

Ryde Pierhead

Ryde Pierhead (IOW Platform Refurb Scheme) for OSL Global (South Western Railway)

Pierhead station is approximately 120 m long and varies in width. The entire structure is a steel structure set over the sea, mainly encased in concrete. Adjacent sectiopns of the disused pier were in poor condition.

Date:              12th March 2021

Client:            OSL Global

Location:       Isle of Wight

Station:          Ryde Pierhead

The scheme was to raise the platform gauge by 400mm and close off the rear section of the platform with a handrail system to prevent passengers accessing a disused section of the platform.

Hammond ‘Mountbridge’ platform systemTM was installed. The works were completed in four shifts for the main platform works. Additional access ramps with dda handrails were installed to the pierhead end.

Project constraints

PTI
Site Access
Public Interface

Risqs Audited
Risqs Verified
ISO 9001
ISO 14001
ISO 45001
Constructionline Gold
Passenger Safety
Subcontractor

Ryde Esplanade

Ryde Esplanade

Ryde Esplanade (IOW Platform Refurb Scheme) for OSL Global (South Western Railway)

The works at Ryde Esplanade station comprised the installation of ‘Mountbridge’ raised platform system.

Date:              12th March 2021

Client:            OSL Global

Location:       Isle of Wight

Station:          Ryde Esplanade

The platform radius was set on a very tight convex curve. The platform was part traditional build and part steel pier construction set over the sea. Adjacent stations were Ryde Pierhead and Ryde St Johns.

Due to increases in platform height to suit the new passenger trains the existing rear platform fences were extended in height.

Project constraints

PTI
Site Access

Risqs Audited
Risqs Verified
ISO 9001
ISO 14001
ISO 45001
Constructionline Gold
Passenger Safety
Subcontractor

Lake Station

Lake Station

Lake Station (IOW Platform Refurb Scheme) for OSL Global (South Western Railway)

Lake station on the Isle of Wight is approximately 80 m in length but quite narrow in cross section and is entirely constructed of a timber supporting structure set on concrete piles.

Date:              12th March 2021

Client:            OSL Global

Location:       Isle of Wight

Station:          Lake Station

The platform was raised approximately 300mm utilising Hammond ‘Mountbridge’ platform system overlaid with dura frp deck set on adjustable pedestals.

The rear fences were replaced, and the entrance ramp modified.

Project constraints

PTI
Site Access
Public Interface

Risqs Audited
Risqs Verified
ISO 9001
ISO 14001
ISO 45001
Constructionline Gold
Passenger Safety
Subcontractor

Needham Market Railway Station

Needham Market Railway Station

Needham Market Railway Station for Abellio Greater Anglia

Existing platform 2 was an insitu cast concrete deck in poor condition, and placed on a bullhead rail steel substructure.

Date:              12th March 2021

Client:           Abellio Greater Anglia

Location:       Suffolk

Station:          Needham Market

During a 52 hour possession, the entire concrete deck was removed and replaced with Hammond Mountbridge adjustable frp platform systemTM. (Patent no 2515519).

The entire length of platform was replaced in approximately 36 hours within the possession period. Further works undertaken included re-surfacing platform 1, and re-lining an existing subway.

Project constraints

Ecology (adjacent country park)
PTI
Planning (liaison with parks department)
Public Interface
Limited possession periods
Plant and material delivery logistics

Risqs Audited
Risqs Verified
ISO 9001
ISO 14001
ISO 45001
Constructionline Gold
Passenger Safety
Subcontractor

Elephant & Castle

Elephant & Castle

Elephant & Castle Station for Network Rail, South East Region

The existing platform construction comprised of an elevated precast concrete platform, (8 metre above road level) mounted above the original brick arch viaduct, the existing platform was then overlaid with 100mm deep asphalt finish.

Date:              12th March 2021

Client:            Network Rail

Location:       London

Station:          Elephant & Castle

The Mountbridge adjustable frp platform systemTM (Patent no 2515519) was overlaid above this construction to overcome the severe stepping distance issues at the platform. There was a requirement to raise the platform level by 150/200mm and similar figures for oversail.

Project constraints

PTI
Public Interface
Limited track possession
Keeping station operational
Limited possession periods
Ecology

Risqs Audited
Risqs Verified
ISO 9001
ISO 14001
ISO 45001
Constructionline Gold
Passenger Safety
Subcontractor

Sandown Station

Sandown Station

Sandown Station (IOW Platform Refurb Scheme) for OSL Global (South Western Railway)

Sandown station is located on the Isle of Wight. The works at Sandown P1 and P2 required the platform gauging height to be increased by approx. 300mm.

Date:              12th March 2021

Client:            OSL Global

Location:       Isle of Wight

Station:          Sandown

To platform 1 and 2 the existing platform was overlaid with Hammond ‘Mountbridge adjustable platform system TM, and incorporates permanent white lining and tactile paving.

During the course of the works a large passenger shelter was also raised, and ramps installed to improve dda access to the platforms.

Project constraints

PTI
Site Access
Public Interface
Pedestrian management

Risqs Audited
Risqs Verified
ISO 9001
ISO 14001
ISO 45001
Constructionline Gold
Passenger Safety
Subcontractor