Existing platform 2 was an insitu cast concrete deck in poor condition, and placed on a bullhead rail steel substructure.
Date: 12th March 2021
Client: Abellio Greater Anglia
Location: Suffolk
Station: Needham Market
During a 52 hour possession, the entire concrete deck was removed and replaced with Hammond Mountbridge adjustable frp platform systemTM. (Patent no 2515519).
The entire length of platform was replaced in approximately 36 hours within the possession period. Further works undertaken included re-surfacing platform 1, and re-lining an existing subway.
Project constraints
Ecology (adjacent country park)
PTI
Planning (liaison with parks department)
Public Interface
Limited possession periods
Plant and material delivery logistics